L
lee.bridle
OK, so, I have the following data:
Batch Start Date and Time - 10/12/08 14:00
Batch Finish Date and Time - 15/12/08 16:55
Batch Duration - =SUM(B2-A2) Which supplies me with the answer: 5.12
However, we shut down over the weekend, so I need to remove the
weekend from the answer, which would give me 3.12.
Trying to do this using Networkdays doesn't seem to include the hours,
so I just get the answer 4, as it touched 4 working days.
Anyone know of something that could help me?
Thanks in advance!
Lee
Batch Start Date and Time - 10/12/08 14:00
Batch Finish Date and Time - 15/12/08 16:55
Batch Duration - =SUM(B2-A2) Which supplies me with the answer: 5.12
However, we shut down over the weekend, so I need to remove the
weekend from the answer, which would give me 3.12.
Trying to do this using Networkdays doesn't seem to include the hours,
so I just get the answer 4, as it touched 4 working days.
Anyone know of something that could help me?
Thanks in advance!
Lee