Dates - can they be dynamic?

  • Thread starter Thread starter John
  • Start date Start date
J

John

Hello.
I need to do a project plan in Excel.
What is the best way to automatically slide date values if dependant project
dates change (slide)?
Thanks!!
 
THANK YOU!

CLR said:
Make one date dependant on the other........ie: if yu have your master
date
in A1, then in B1 you could have =A1+7 and it would return a date one week
later than that in A1.....if you put in C1 either =A1+14, or =B1+7, then
C1
qould return a date two weeks after that in A1, etc etc.......change A1
and
they all change purpotionally

hth
Vaya con Dios,
Chuck, CABGx3
 
And I thank you too. This is a handy little shortcut. I don't need to do
this often, but from time to time I can use this. Again, thanks!
 