I would like to subtract and add (in two different columns), 2 WORK DAYS from
a given date. Does anyone know how to do this?
 
=WORKDAY(A2,2,Holidays)

=WORKDAY(A2,-2,Holidays)

look it up in help

--


Regards,


Peo Sjoblom
 
Thanks for the info, but I keep getting an error message #name? Any thoughts?
 
Thanks for the info, but I keep getting an error message #name? Any thoughts?


You don't have the ATP installed.

If you look at HELP for the WORKDAY function, you will see that error listed
and also how to fix it.
--ron
 
Any other suggestions? I do have the toolpac loaded and installed....I redid
it, but nothing..
 
IT HAS BEEN FIXED! THANKS EVERYONE!

Steve said:
Any other suggestions? I do have the toolpac loaded and installed....I redid
it, but nothing..
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Back
Top