Selva
How do i get the the finish date using the excel sheet for the following
scenerio.
Start date : 1-Dec-08
Duration : 6 days
Holiday : 8-Dec-08
Finish date : 9-Dec-08 (exculdes the weekends & Holiday)
scenerio.
Start date : 1-Dec-08
Duration : 6 days
Holiday : 8-Dec-08
Finish date : 9-Dec-08 (exculdes the weekends & Holiday)