How do I calculate days between dates using a 5 day calendar with Thursday
and Friday as the weekend days? Thank you.
 
Hi
try
=NETWORKDAYS(A1+1,A2+1)

where A1 and A2 are your two starting days
 
Hi, Frank:

I think you need to add 2, so Excel will "think" that Thu is Sat, and Fri is
Sun.
 