G
Guest
Hello all,
For each group of participants I have two phases, Orientation and
Probation. I have the Orientation Start Date and the Probation Start Date
stored in a table for each group.
Project completion dates are recorded in a seperate table. As projects
are completed, I need to determine during which phase and (whole) week they
were completed.
Example: Orientation Start Date of 1/1/06, nearest Monday is 1/2/06
Probation Start Date 2/1/06, nearest Monday is 2/6/06
First Project completed 1/6/06 means Orientation Week 1
Second Project completed 1/17/06 means Orientation Week 3
Third Project completed 2/2/06 means Orientation Week 5
Fourth Project completed 2/16/06 means Probation Week 2
Esentially I need to say:
If Completion_Date is < P_Start_Date, then it is Orientation Week X
If Completion_Date is >= P_Start_Date, then it is Probation Week X
I would appreciate any help! Thank you much!!
Renee
For each group of participants I have two phases, Orientation and
Probation. I have the Orientation Start Date and the Probation Start Date
stored in a table for each group.
Project completion dates are recorded in a seperate table. As projects
are completed, I need to determine during which phase and (whole) week they
were completed.
Example: Orientation Start Date of 1/1/06, nearest Monday is 1/2/06
Probation Start Date 2/1/06, nearest Monday is 2/6/06
First Project completed 1/6/06 means Orientation Week 1
Second Project completed 1/17/06 means Orientation Week 3
Third Project completed 2/2/06 means Orientation Week 5
Fourth Project completed 2/16/06 means Probation Week 2
Esentially I need to say:
If Completion_Date is < P_Start_Date, then it is Orientation Week X
If Completion_Date is >= P_Start_Date, then it is Probation Week X
I would appreciate any help! Thank you much!!
Renee