In the Task view window, I have the tasks sorted by
Category and all of the tasks in each category are sorted
by due date, even the completed tasks. However, I don't
want the completed tasks to show in this screen. How can
I hide them?

Thanks,

Terry B.
 
Create a filter for that view with the criteria "Complete equals no" -- you
can do this on the Advanced tab of the Filter dialog.

--