Can anyone advise me how to calculate the number of working days? Obviously
calculating the number of days between 2 dates is easy, but is there an
expression to use which returns the number of working days?

Many thanks.

Will
 
Hi Will

check out the NETWORKDAYS function in help ... it's part of the analysis
tool-pak add-in

Cheers
JulieD
 
=NETWORKDAYS(start_date,end_date,holidays)

holidays is an optional argument to avoid counting holidays. This would be a
worksheet range.

This function is part of the Analysis Toolpak, so you need that to be
installed.


--

HTH

RP
(remove nothere from the email address if mailing direct)
 
Many thanks everyone.

Will

Bob Phillips said:
=NETWORKDAYS(start_date,end_date,holidays)

holidays is an optional argument to avoid counting holidays. This would be a
worksheet range.

This function is part of the Analysis Toolpak, so you need that to be
installed.


--

HTH

RP
(remove nothere from the email address if mailing direct)
 
Other approach (without holidays, calculating from 24:00
of first date to 24:00 of second date):

=(A2-WEEKDAY(A2,2)+WEEKDAY(A1,2)-A1)/7*5-MIN(5,WEEKDAY
(A1,2))+MIN(5,WEEKDAY(A2,2))

HTH,
Bernd
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Back
Top