I need to calculate how many business days between 2 dates.
G2 is report submission date
H2 is report reviewed date
K2 is the result - how many days it took to review the report
My formula is =if(or(isblank(G2),isblank(H2)),"",networkdays(G2,H2))
This formula produces #NAME? in K2
How do I fix the formula (I am using Excel 2003)?
 
Type the word "networkdays" into Excel help, and see what it tells you.
 
Type the word "networkdays" into Excel help, and see what it tells you.
 
Nevermind. Thank you. I already got my answer. It requires Tools => Add-Ins
==> Analisys ToolPac installed and the formula should be:
=IF(OR(ISBLANK(G2),ISBLANK(H2)),"",(NETWORKDAYS(G2,H2)-1))
 
Nevermind. Thank you. I already got my answer. It requires Tools => Add-Ins
==> Analisys ToolPac installed and the formula should be:
=IF(OR(ISBLANK(G2),ISBLANK(H2)),"",(NETWORKDAYS(G2,H2)-1))
 