A
Alankar.Trivedi
Hi,
I have assigned tasks to members of my project team via outlook
(Outlook 2007) and those tasks have been accepted. These tasks have
been accepted by those members. These tasks are the same that are on
my Microsoft Project Plan (Project 2003)
Every morning they update the % Complete field in Outlook for the
tasks they have been assigned.
Every morning I then have to go in to my project plan and fill in the
% Completion field myself.
Is there some way or some add in that when a member updates the %
complete in Outlook that the % complete field for the related task in
Project is also completed at the same time.
Thanks
I have assigned tasks to members of my project team via outlook
(Outlook 2007) and those tasks have been accepted. These tasks have
been accepted by those members. These tasks are the same that are on
my Microsoft Project Plan (Project 2003)
Every morning they update the % Complete field in Outlook for the
tasks they have been assigned.
Every morning I then have to go in to my project plan and fill in the
% Completion field myself.
Is there some way or some add in that when a member updates the %
complete in Outlook that the % complete field for the related task in
Project is also completed at the same time.
Thanks