R
roniaelm
Hi,
I wish to calculate the number of weekdays a project is recorded
against. In my list I can have multiple of the same weekday for a
specific project and task but I wish excel to only calculate it as 1
day for example:
Mon 1-Dec-08 Artwork Draw
Mon 1-Dec-08 Artwork Paint
Tue 2-Dec-08
Wed 3-Dec-08 Artwork Paint
Artwork was actually completed over 2 days not 3 how do I get excel to
calculate 2 days and not 3?
Thanks soo much!
I wish to calculate the number of weekdays a project is recorded
against. In my list I can have multiple of the same weekday for a
specific project and task but I wish excel to only calculate it as 1
day for example:
Mon 1-Dec-08 Artwork Draw
Mon 1-Dec-08 Artwork Paint
Tue 2-Dec-08
Wed 3-Dec-08 Artwork Paint
Artwork was actually completed over 2 days not 3 how do I get excel to
calculate 2 days and not 3?
Thanks soo much!