On the 3rd Wednesday of each month I have to produce reports for one of my
customers to be presented to the board of directors. The report is created
and sent 2 days prior to the 3rd Wednesday so they have time to review them.

How do I schedule this. I cannot use 3rd Monday of each month as for this
month it would be a week late. (3rd Monday is 20th but 3rd Wednesday is
15th). I need to schedule before the 3rd Wednesday.

Is there some way of scheduling it for 2 days before the 3rd Wednesday of
each month?

Craig
 
Couldn't you schedule it for the 3rd Wednesday and set the notification to 2
days prior?
 