Formula on Actual Vs Plan

  • Thread starter Thread starter Eddy
  • Start date Start date
E

Eddy

Hi Friends!
Could some help me on this formula?
I need to complete a task say from 1-Jun-05 to 30-Jun-05 i.e 30 days,
but however on a given day when I analyse the Project schedule (say
today), I find out that on the 9th day i.e 9-Jun-05 on actual progress
I have completed only 4% of the Job, Hence what should be my forecasted
days to complete the job a 100% in actual, now putting it in a
mathematical sense:
100% = 30days (Plan)
4% = 9days (Actual & when the plan is 30%)
Hence 96% = ? (How may days in Forecast)

I want the formula to be dynamic, such that on the 15 day if I catch up
with my plan I will be 50% in Actual but if on the 28th day I am still
say 65% in Actual then what would be the forcasted days or total days
to still complete my work a 100% in actual

Any help would be very appreciated
Regards
Edward
 
If I understand you correctly, one way:

If A1 = start date, and B1 = %complete, then if 4% complete after 9
days, the total job will be 225 days (9/4%), with 216 days remaining:

=(TODAY()-A1+1)*(1/B1-1)
 
Try this
Cell G1 contains the project start date

A2 contains the current date, B2 has the current completion %.
C2 contains =+(100/B2)*(A2-G$2) which will return total project days a
current rate
=+G$2+C2 then shows forecast completion date
=+C2-(A2-G$2) will show number of days left befre completion (a
current rate)

Hope this help
 
Alex said:
Try this
Cell G1 contains the project start date

A2 contains the current date, B2 has the current completion %.
C2 contains =+(100/B2)*(A2-G$2) which will return total project days at
current rate
=+G$2+C2 then shows forecast completion date
=+C2-(A2-G$2) will show number of days left befre completion (at
current rate)

Hope this helps

Thanks for your replies, but I think you all are missing the point. I
think you are ignoring either the Finish date or the Plan percentage
completion. I would appreciate if you took this into consideration,
Edward
 
Then you need to be more explicit. The answers you got were pretty
consistent with the amount of information you gave.

To use your example, with a 30 day plan, if you find you're 4% done on
day 9, how should one factor in the Finish date or plan percentage in
calculating "forcasted days" or total days to complete?

Seems to me that if you're 4% done after 9 days, you're completing 4/9%
per day, and it will take you 24*9 (216) additional days to finish, no
matter what the plan said.
 
How is the percentage of completion being determined? Is it manually
entered or computed using a formula?

Jerry
 
Back
Top