Thre are a few ways by which you can accomplish what you want:
Let's suppose that column flow rates (GPM) are in A2:A14, Pump Pressure are
in B2:B14, and System Pressure are in C2:C14. Create a column D2

14 as
follows:
In D2 enter the formula =B2-C2, and drag the formula down to D14.
Method 1 (Maybe Good!):
By making an inverse plot (a slightly approximate, but very quick, solution)
Make a plot of A2:A14 (Y-axis) and D2

14 (X-axis) and fit a polynomial
(maybe, 3-rd order) and get the trendline equation. The constant term is
what you want. Unfortunately, this result may be about 2-4% off from the
'correct' value. For example, for your data, the result from this approach
is 2952 gpm (the trendline equation is y = 1E-08x3 - 0.0001x2 + 0.8402x +
2952.2) is about 2% off from the correct value (2891 gpm)
A convenient aspect of this method is that the trendline equation would
automatically update when your original data change.
Method 2 (Better?):
You can use Solver, and solve for the flow rate for which the difference
between Pump Pressure and System Pressure will be zero. Obtain the trendline
equation for The result obtained would be very good (e.g., 2891 for your
samnple data). However the inconvenient aspect is that the result WILL NOT
update when your original data change(s). You have to manually invoke Solver
every time that happens.
Method 3 (Best!): Exploiting Circular Reference.
Select a 1 Row x 4 Column area, and entering the following formula,
=LINEST(D2

14,A2:A14^{1,2,3}), confirmed with CTRL-SHIFT-ENTER
(for your sample data, 2.029E-09, 2.211E-04, 8.974E-02, -2.156E+03)
In E2, enter an arbitrary flow rate (gpm) value, say 300.
In F2, =1.00001*E2
IN G2, =a*E2^3+b*E2^2+c*E2+d (where a, b, c, and d are the actual
values of the coefficients from the trendline equation or linest function)
In H2, =a*F2^3+b*F2^2+c*F2+d
In I2, =(H2-G2)/(F2-E2)
In J2, =(I2*E2-G2)/I2
Now comes the interesting part. Go back to E2 and enter =J2.
Excel will complain and say there is a Circular Reference. Ignore that. Go
to "Tools" --> "Options" --> "Calculation" Tab, check "Iteration" --> "OK"
Now Excel will accept the circular reference. You would notice that E2 and
J2 have become equal. That is the value you want! Your sample data yielded
the following results:
2890.9 2891.0 0.0 0.0 1.4 2890.9
The values will update when your original data change.
Regards,
B. R. Ramachandran