how can i set a work rota that is in the working time directive and also
rotates names each week |
|
|
|
#2 |
|
Guest
Posts: n/a
|
That would depend on how many teams there were:-
4 teams is 24*7/4 = 42 hrs/wk 5 teams is 24*7/5 = 33.6 hrs/wk 6 teasm is 24*7/6 = 28 hrs week and the shift length 8hrs or 12 hrs or some hybrid system. The EWTD directive limits the working week (with exceptions) to 48hrs averaged over a rolling 17 week period and guarantees 11hrs unbroken rest every day. So as you may gather from the information you have provided it's diffiocult to provide too much guidance. have a look here: http://www.dh.gov.uk/en/Policyandgu...ctive/index.htm and here http://web.ukonline.co.uk/bjlogie/schedules.htm Mike "Toady" wrote: > how can i set a work rota that is in the working time directive and also > rotates names each week |
|
![]() |
|
| Thread Tools | |
| Rate This Thread | |
|
|

Main Page 