I have seen some strange collapsing behaviour many times. Try this:
Right click the column header of the Task table and selelct customise
current view. Bottom right corner are the expand/collapse settings. Set
to show all expanded. OK. Then do it again. No Really! DO THIS TWICE. It's a
bug that's been around for eons.
Judy Gleeson, Microsoft Most Valuable Professional, Outlook
Director, Acorn Training and Consulting
Author - Productiv_IT with Outlook
www.acorntraining.com.au
"T. Wise" <(E-Mail Removed)> wrote in message
news:(E-Mail Removed)...
> If I create a Task item and then look at the Tasks in Table View (grouped
> by Category), I sometimes find that the Group to which the new Task was
> assigned is collapsed. I can expand that group, and all is fine, but if I
> create another Task in another Category, that will sometimes cause that
> group to collapse.
>
> I haven't been able to figure out exactly when this happens, but it seems
> to happen more often when I'm switching between Views. i.e, if I create a
> Task while in one Table View (filtered for high priority items only) and
> then switch to the other Table View (no filter), the new task is in a
> collapsed group.
>
> Anything I can do about this?
>
> I'm using OL 2003, WinXP Pro SP2.
>