Creating a Project Schedule, displaying the hours per day.

 
 
Paul Monsef
Guest
Posts: n/a
 
      18th Feb 2008
I am wondering if it's possible to create a spreadsheet with a start date, #
of hours and dates along the top... When the hours are updated I'd like the #
of hours per day to be worked on the project timeline.

Hopefully that makes some sense.

--

Paul Monsef
Monsef Consulting and Design

 
Reply With Quote
 
 
 
 
Gary''s Student
Guest
Posts: n/a
 
      18th Feb 2008
http://office.microsoft.com/en-us/te...CT101436151033
--
Gary''s Student - gsnu200769


"Paul Monsef" wrote:

> I am wondering if it's possible to create a spreadsheet with a start date, #
> of hours and dates along the top... When the hours are updated I'd like the #
> of hours per day to be worked on the project timeline.
>
> Hopefully that makes some sense.
>
> --
>
> Paul Monsef
> Monsef Consulting and Design
>

 
Reply With Quote
 
Paul Monsef
Guest
Posts: n/a
 
      20th Feb 2008
Thanks for the reply.

I was looking for like type of format:
http://www.monsefdesign.com/ProjectS...s-Timeline.mht

Where, the individual days are filled in via conditional formatting. I guess
it's more of a 'timline' approach than the example you sent. I have to fill
in the hours manually, I was hoping for a way to have the total hours
distributed across the 'blue cells' automatically.

Thanks again for any aid.

--

Paul Monsef
Monsef Consulting and Design



"Gary''s Student" wrote:

> http://office.microsoft.com/en-us/te...CT101436151033
> --
> Gary''s Student - gsnu200769
>
>
> "Paul Monsef" wrote:
>
> > I am wondering if it's possible to create a spreadsheet with a start date, #
> > of hours and dates along the top... When the hours are updated I'd like the #
> > of hours per day to be worked on the project timeline.
> >
> > Hopefully that makes some sense.
> >
> > --
> >
> > Paul Monsef
> > Monsef Consulting and Design
> >

 
Reply With Quote
 
 
 
Reply

Thread Tools
Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Creating a formula to display # of work hours spent on a project =?Utf-8?B?S2VycnlNMTIxMg==?= Microsoft Excel Misc 1 3rd Aug 2007 06:22 PM
employee schedule with hours =?Utf-8?B?RGF3biBQ?= Microsoft Excel Worksheet Functions 3 1st Aug 2007 02:14 PM
Schedule hours calculation =?Utf-8?B?UkogU3dhaW4=?= Microsoft Excel Misc 6 21st Nov 2006 09:32 PM
need to schedule a task every few hours jd Microsoft Windows 2000 4 21st Apr 2005 02:29 PM
Schedule hours total jason Microsoft Excel Worksheet Functions 1 8th Jan 2004 04:41 PM


Features
 

Advertising
 

Newsgroups
 


All times are GMT +1. The time now is 01:28 AM.