p45cal,
Your formula works great thanks again. Got one more question if you do not
mind. With this spreedsheet I am not only tracking how much time is required
to complete all of the steps and when they should be finished with one step
and on to the next, but I am also tracking when the process was started and
when the parts are due.
Customer
File # P11672
Due Date: 7/18/07
Released: 7/12/07 8:17 AM
Workdays: #VALUE!
My problem is I get an Value error.
In the released colum I am using =Now() and in the work days I am using
=NETWORKDAYS(C5,D10,NETWORKDAYS!C1:C10)
C5 is the due date, D10 is the first process step and NETWORKDAYS is another
work sheet that has all of the holidays.
Hope this enough information
Regards
Scott
"p45cal" wrote:
> I made a mistake when I said that the formula you gave me ended the week Sat
> 1am and started on Mon 8am. On testing on my PC with XL2003 the week ends Fri
> 1am and starts Sun 8am. Do you run this on Excel on a Mac?
>
> The following formula uses Sat 1am as the end of the working week and Mon
> 8am as the start. If it uses the wrong days for the weekend on your system,
> you may have to change the =7 back to =6.
>
> It seems to work well on cursory testing, BUT YOU WILL HAVE TO CHECK IT OUT
> THOROUGHLY YOURSELF. This belongs in cell D21:
>
> =IF(A21="","",IF(AND((MOD(D20,1)+(VLOOKUP(A21,'WORK
> STEPS'!D$2:E$39,2,TRUE))>0.041666),MOD(D20,1)<0.333333,WEEKDAY(D20,1)=7),ROUNDDOWN(D20,0)+2.333333+VLOOKUP(A21,'WORK
> STEPS'!D$2:E$39,2,TRUE),D20+VLOOKUP(A21,'WORK STEPS'!D$2:E$39,2,TRUE)))
>
> and can be filled down and/or up the column.
>
> ps. You gave very little information out, I had to work out or make
> assumptions for myself about where things were, what kind of data it was.
> Normally, on viewing posts with such sparse information I would have passed
> onto another question, but unusually, I had time to kill. If you can't be
> bothered to supply full details, why should others be bothered to look at
> your problem? Help others to help you. OK, lecture over, hope this fits the
> bill.
>
> --
> p45cal
>
>
> "Scott W" wrote:
>
> > I do need to go 24 hours per day but only until Saturday 1:00Am and start
> > again on Monday at 8:00AM. I really appreciate your help.
> >
> > Thanks
> >
> > Scott
> >
> > "p45cal" wrote:
> >
> > > Right, the formula you gave allows steps to go on until 1am; if they would go
> > > beyond 1am then that step starts at 8am next morning instead. A 17 hour day.
> > > The formula you gave also takes into account weekends, with the last job
> > > having to be finished before Saturday 1am, Monday 8am being the next start
> > > time.
> > >
> > > Do you still want weekends taken into acount? If so, is the end of the week
> > > still 1am Saturday, and start of the week 8am Monday? Or is production now
> > > truly 24/7?
> > >
> > > --
> > > p45cal
|