To show the weeks in my 3rd column, I used:
=(networkdays(A1,B1))/5
and it seems to work. Is this an accurate way to modify the formula to show
weeks?
Thanks!
"Britt" wrote:
> Hey there,
>
> First make sure these cells are formatted as dates (and not text)
> Ensure you have the ATP (go to tools, add-ins and check the box next to
> Analysis Toolpak)
> Then use the NETWORKDAYS function (formula)
> for instance
> col A = start date
> col B = end date
> col C = duration (in working days)
> (opt) col D = could be the number of weeks or any other calculation
>
>
> For example, col C will be your formula...
> If A1 = 3/16/07
> If B1 = 4/2/07
> C1 will need the following pasted into it:
>
> =NETWORKDAYS(A1,B1)
>
> This formula calculates the number of working days between 2 dates.
> Your result here should be 12
>
> You could then do a SUM function in the next column to divide the network
> days to give you an approx week calculation
>
> Hope it helps!
> -Britt
>
>
> "vnsrod2000" wrote:
>
> > Hello. I have three columns:
> > start date
> > end date
> > duration
> > What function do I use to calculate the number of weeks the dates entered in
> > the first two columns?
> >
> > Thanks.
|