How do i change the workday function to a 6 day week?
I don't think you can. I didn't realize that you were working with a 6 day
week when I replied.
--
Regards,
OssieMac
"primed" wrote:
> Hi OssieMac,
>
> How do i change the workday function to a 6 day week?
>
> "OssieMac" wrote:
>
> > Have a look in Help for the worksheet function Workday. I feel sure that it
> > will help you to do what you want.
> >
> > As this is an Excel programming site, then you possibly want to use it with
> > VBA. if so, then the code is as follows.
> > WorksheetFunction.WorkDay(start_date,days,holidays)
> >
> > Could also look at NETWORKDAYS function. use it similarly to above in VBA.
> >
> > --
> > Regards,
> >
> > OssieMac
> >
> >
> > "primed" wrote:
> >
> > > Hi,
> > >
> > > I need help converting working days to calendar days, to give me a
> > > completion date.
> > >
> > > I have a calendar (sheet name "Calendar") with the following columns
> > > Column A - Date
> > > Column B - Day of week (ie 1 to 7, 1 being a Sunday).
> > > Column C - Non Working Days (contains a 1 if the row is a Sunday)
> > > Column D - Holidays (contains a 1 if the row is a public holiday)
> > > Headings are row 1, Data is row 2 to Row 1872
> > >
> > > My second sheet is called "EOT Register". This contains a summary of how the
> > > completion date was calculated.
> > >
> > > Column F contains the start date(f2:f72)
> > > Column I contains the number of work days which needs to be added.
> > > Column K should total the number of Non working days ie Sundays between the
> > > start date and completion date
> > > Column M should total the number of holidays between the start date and
> > > completion date
> > > column N is where the calendar days needs to be calculated
> > > Column P is where the completion date needs to be calculated(Col F+ Col N)
> > >
> > > Columns K,M,N,P are the columns that i need help with.
> > >
> > > Regards
> > > Primed
|