Hello There - I need some help here. I did search the entire forum and seems like no one has posted this question before.

Background
==========
Approval received date: 31-Dec-2010
Work should start within 2 working days

So i need to find the formula that can give me the result of 31-Dec-2010 + 2 working days =
4-Jan-2011 (minus weekends)

I tried to use the NETWORKDAYS formula but no luck.

Thanks,
Mazu
Attached Thumbnails
Adding days by using NETWORKDAYS 2007 formula-start_date.jpg  
 
Reply With Quote
 
 
 
Reply

Thread Tools
Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Adding days by using NETWORKDAYS 2007 formula tiger7ail Webmaster / Programming 0 6th Jan 2011 03:28 PM
Formula adding 2 days... Zoe Microsoft Excel Misc 2 15th Apr 2010 11:51 PM
networkdays - Excel 2007 drops some days Bill Roberts Microsoft Excel Discussion 9 17th Feb 2009 11:20 PM
how to use networkdays returning fractions of days (4.3 days) =?Utf-8?B?Q2hyaXM=?= Microsoft Excel Worksheet Functions 0 6th Oct 2005 03:19 PM
NETWORKDAYS formula to exclude weekends, holidays and days not worked by part-timers junglejinge Microsoft Excel Worksheet Functions 0 2nd Aug 2004 02:56 PM


Features
 

Advertising
 

Newsgroups
 


All times are GMT +1. The time now is 01:53 AM.